2023/2024 Pavement Management Program

2023/2024 Pavement Management Program

Information is updated as it becomes available. We strive to provide 3-5 days advance notice for abutters to a road reconstruction project, however there are occasions when contractor availability or unforeseen conditions delay or accelerate the schedule. When this occurs we make every effort to notify residents as soon as possible.
 
All projected dates are subject to change and are weather permitting.
 
STREETFROMTO
CHESTER RDOAKLEY RD

COMMON ST

HAMMOND RDPALFREY RDGILBERT RD
FLETCHER RDTYLER RDCLIFTON RD
WASHINGTON STCOMMON STGODEN ST
BRIGHT RD (SB Lane)WASHINGTON STCONCORD AVE
MILL STSTANLEY RD300' N OF TRAPELO RD
  • BID OPENING 9/8/2023
  • NOTICE TO PROCEED 9/28/2023
  • SEWER ESTIMATED START DATE 12/11/2023
  • ROADWAY ESTIMATED START DATE 5/1/2024

UTILITY WORK SCHEDULE

STREETSEWER/DRAIN
START

SEWER/DRAIN

END

CHESTER RD

12/19/23

12/21/23
HAMMOND RD12/12/2312/15/23
FLETCHER RD1/2/241/5/24
WASHINGTON ST12/20/2312/21/23
BRIGHT RD (SB Lane)1/29/24 
MILL ST12/28/231/9/24

ROAD CONSTRUCTION

STREETLOWER UTILITY
STRUCTURES
RECLAMATIONASPHAULT
BINDER
ACCESSIBLE
RAMPS
FINAL
PAVING

CHESTER RD

4/8/24-4/9/244/29/24-5/3/245/3/24

5/6/24

 
HAMMOND RD4/9/244/29/24-5/3/245/3/24

5/6/24

 
FLETCHER RD     
WASHINGTON ST     
BRIGHT RD 
(SB Lane)
 5/28/245/29/24 

5/29/24

MILL ST     
COMMON ST &
BELMONT ST
(Intersection)
 5/28/245/29/24 5/30/24