What happens to the high school students while the new school is being built?

The Construction Manager will develop a strategy for phased construction and occupancy of the 7-12 school. New construction will be done first, such that 9-12 students can remain in the existing structure until they can occupy new areas of the school. Once the 9-12 area of the school is finalized, high school students will utilize the 9-12 portion of the school. At this time, construction will commence on the 7-8 portion of the school. All efforts will be made to minimize disruption to school operations and to maintain safety and security for students, faculty, and staff. This may include utilization of temporary walls and partitions, as well as temporary student drop-off areas and traffic patterns.