When will the town vote on funding the full High School Building Project?

The MSBA’s schedule to complete the Feasibility Study and Schematic Design phases and secure funding for the full project must be completed by May 2019. The Belmont High School Building Committee is scheduling to meet that deadline with a vote in November 2018 or in April 2019.