Project Status Graphic

Project Timeline and Process

 

The current schedule for the project is:

Completion of Feasibility Study - Spring 2018

Completion of Preferred Schematic Design - Summer 2018

Secure Project Funding - November 2018 or April 2019

Completion of Building Design - TBD (approximately 12-15 months)

Completion of Building Construction - TBD (approximately 24-36 months)