11/10/09
The Concord Ave Water Main Replacement Project has been completed from Pleasant Street to Mill Street. Concord Ave is now open to through traffic. Construction on Concord Ave from Winter Street to the Lexington town line will continue through November weather permitting.
The Department of Public Works Water Division is continuing the water system improvement program with a water main replacement project on Concord Avenue
between Pleasant Street and Robin Wood Road.
Work will be performed by Cedrone Trucking Company under contract with the Town and is planned to start in mid August and continue until the end of November.
Over the next few months Concord Avenue from Pleasant Street to Mill Street
will be closed to through traffic from 7:00 AM until 5:00 PM weekdays with access only to abutters.
Generally, at other times Concord Ave. will be open to through traffic. Detour signs will be provided to guide motorists around the work area as necessary.
You may visit the “News and Notices” section of the Town of Belmont Web site at
www.belmont-ma.gov for up to date information or you can call the Department of Public Works at 617-993-2680 with questions.
We regret any inconvenience and thank you for your patience during this important improvement program.
|